Sustainment, Restoration, and Modernization Task Order Contract (SATOC) |
Contract No.
Scope of Work:
Period of Performance:
Award Ceiling:
Contract Location: |
FA3002-08-D-0017
Construction and engineering activities supporting the Sustainment, Restoration, and Modernization (S/R&M) of real property worldwide. Depending on the project development stage and level of design required for each project, work may utilize Turnkey, Design-Build (DB), Design-Build Plus (DB+), Conceptual/Implementation Work Plan Construction (CWP/IWP), or Traditional Construction approaches to meet the installations requirements.
May 2008 to May 2018 - 5 year basic ordering period and 5 option years.
$2 Billion with a potential to increase to $4 Billion
Worldwide including remote, austere and hostile locations. |
| |
U.S. Air Force: Heavy Engineering Repair and Construction (HERC) |
Contract No.
Scope of Work:
Period of Performance:
Award Ceiling:
Contract Location: |
FA8903-06-D-8503
Provide heavy construction and engineering activities at DoD sites worldwide; including the full range of methods and technologies supporting activities necessary to design and construct new facilities and infrastructure, and remodel and upgrade existing facilities and infrastructure. May include environmental work incidental to construction.
April 2006 to April 2011 (5-year basic ordering period, plus 3 additional 1-year options)
$6 Billion
Worldwide |
| |
U.S. Army Engineering and Support Center, Huntsville: Facility Reduction Program ID/IQ |
Contract No.
Scope of Work:
Period of Performance:
Award Ceiling:
Contract Location: |
W912DY-05-D-0011
Demolition Services – Facility Reduction Program
May 2005 to May 2010
$15 Million
Continental US |
| |
| Naval Facilities Engineering Command: Environmental Multiple Award Contract (EMAC) |
Contract No.
Scope of Work:
Period of Performance:
Award Ceiling:
Contract Location: |
N62472-05-D-0032
8(a) contract to provide environmental remediation services at Navy installations in New England, New York, New Jersey, Pennsylvania,
and Delaware.
September 2005 – September
2006 (1 base year with 4 option years)
$30 Million
Northeastern US-10 State Area |
| |
Air Force Center for Environmental Excellence: Environmental Construction and Operation Services (ECOS) ID/IQ |
Contract No.
Scope of Work:
Period of Performance:
Award Ceiling:
Contract Location: |
FA8903-04-D-8723
The ECOS contract offers a broad range of construction, repair, and demolition work, to include both traditional and environmental; plus force protection and homeland security. In addition, this contract will
provide operations and services for environmental conservation compliance, pollution prevention and clean-up activities, and will include ordnance removal and disposal, energy management, and Geographic Information
Services.
April 2005 to March 2009
$150 Million with a potential to increase to $375 Million
Worldwide |
| |
New Boston Air Force Station: Simplified Acquisition of Base Engineering Requirements (SABER) ID/IQ |
Contract No.
Scope of Work:
Period of Performance:
Award Ceiling:
Contract Location: |
FA2835-05-D-0003
ID/IQ contract to complete renovations of existing facilities, demolition of existing facilities and construction of new facilities at the New Boston Air Force Station
July 2005 to July 2006 (1 base year with 4 option years)
$10 Million
New Boston Air Force Station, New Hampshire |
| |
| USACE New England District, Multiple Award Remediation Contract (MARC) ID/IQ |
Contract No.
Scope of Work:
Period of Performance:
Award Ceiling:
Contract Location: |
W912WJ-06-D-0001
Indefinite Quantity Contract for the Remediation of Hazardous Waste Sites within the Geographic Boundaries of North Atlantic Division.
October 2005 to October 2006 (1 Base Year with 4 Option Years)
$10 million
North Atlantic Division |